Which rulebook will your dock's wiring be measured against when the house sells? For most of the last four decades, a Lake Lanier dock changing hands was recertified against an electrical standard the U.S. Army Corps of Engineers adopted on November 27, 1985. Starting January 1, 2027, that standard is gone. The Corps has approved an administrative change to its 2004 Shoreline Management Plan. Under it, electric service serving a private dock must meet Article 555 of "the most recent version" of the National Electrical Code, and a licensed contractor must certify that at every change of ownership.

So a listing that goes live in November and closes in January can start under one standard and finish under another. For anyone selling or buying a dock home this winter, the closing date now matters about as much as the price.

The calendar now picks the standard

Recertification at a sale is nothing new on Lanier. The 2004 plan already required it "at each permit renewal, change of ownership or at any time an inspection reveals that the service does not meet requirements." What changes on January 1 is the standard the electrician certifies against.

Through December 31, 2026 Effective January 1, 2027
Standard 1985 Corps requirements in Exhibit 3, described as slightly exceeding the NEC The most recent NEC for all service crossing or serving public land; Article 555 of that code for service to private docks
Core rule All electrical service must have GFI protection and be buried underground, with ground-fault protection on all convenience receptacles and lighting Whatever Article 555 requires in the current edition
Older docks All service must meet the rule "regardless of the age, condition or Grandfathered provision" The new text contains no grandfather language at all
Service route and pole Not specified in this section The line follows the access path; one pressure-treated 6x6 wood pole per dock, no taller than 8 feet, unless the NEC requires otherwise
Lighting Shielded, pointed down, not protruding beyond the floating facility Moved to new Section 15.3.15: shielded, pointed down, kept within the outer perimeter of the floating facility
Exhibit 3 In force Deleted, along with every reference to it

Lake folks already know the 1985 standard. A dock that passed recertification under it has been measured against the same checklist for years. Starting in January, the checklist is a national code that NFPA revises on a regular cycle, so the measuring stick for an older dock can now change even when nothing on the dock has.

A letter with a three-month shelf life

The new text spells out the paperwork in detail. The certification has to be an original letter from a state-licensed electrical contractor, no more than three months old, and it has to include:

  • The Corps permit or license number
  • A list of the electrical facilities and components inspected
  • The contractor's printed name and signature
  • The contractor's Georgia electrical contractor's license number
  • The date of inspection

Three months sounds like plenty of time until you lay it over a winter sale. Here's how the dates line up for a dock home listed this fall:

  1. Late October 2026. The seller has an electrician inspect the dock and gets a letter dated now. Ninety days from late October runs into late January.
  2. November and December 2026. Showings, an offer, inspections, appraisal. This is when holiday schedules tend to push closings back.
  3. January 1, 2027. The amended Section 15.3.10 takes effect, and the required letter has to certify compliance with the NEC.
  4. Late January 2027. A letter dated in late October reaches its three-month limit.

A sale that closes cleanly in December stays on the old side of that line. A sale that slips past New Year's ends up holding a letter written for a deleted exhibit, possibly close to its expiration, and due under a new standard. The amendment doesn't say how the Corps will treat a letter or application that straddles the effective date. Anyone with a closing in that window should put that exact question to the Corps directly.

The buyer's paperwork starts after closing

The new owner, not the seller, files for the dock permit, and that filing can't begin until the deed is recorded. Here the dock's timeline and the house's timeline separate.

The Corps' 2026 change of ownership form says the existing Shoreline Use Permit expires when the property changes hands. The permit is tied to the tax parcel identification number, not the owner, and new owners have to apply for a new permit in their own name. Section 15.1 of the plan backs this up: permits are nontransferable, run a maximum of five years, and require new owners to notify the Corps and apply after a sale.

The form asks for four core documents, and each one has its own catch:

  • A recorded deed with the county recording stamp, notary stamp and signature, grantor signature, and the full legal description, usually labeled "Exhibit A." The Corps won't accept closing statements or security deeds.
  • A current survey or plat showing property lines, structures and the lot number or address. In most cases the Corps won't accept subdivision plats, county GIS maps or satellite images, Google Maps included.
  • A scaled drawing of the existing dock, with overall dimensions, slip size, walkway widths, gangway and any roof overhang. Photos can support the drawing but can't replace it.
  • A site drawing showing the Corps property line, private lines, shoreline bank, the path, neighboring docks, and the dock's authorized location, which the form notes "may be different from where the dock is currently located."

Once the package is complete, an Area Ranger reviews it and inspects the shoreline to confirm the facilities and check them against the 2004 Shoreline Management Plan. The Corps' Permit Program page estimates six to eight weeks from receipt of a completed application, and it notes an administrative fee for change of ownership without listing the amount.

Count it out for a mid-November closing. The deed gets recorded, the buyer gathers the survey and drawings, and the six-to-eight-week clock starts. That review can easily run past January 1. A sale can close on the old calendar while the dock paperwork lands on the new one.

What "most recent version" could reach

The amendment points to the most recent NEC without naming an edition, and that leaves a real question. NFPA identifies the 2026 NEC as the current edition. The Georgia Department of Community Affairs lists the 2023 NEC with Georgia amendments as the state's mandatory electrical code, and the changes DCA announced for January 1, 2027 are 2026 Georgia Amendments to the 2023 NEC, not adoption of the 2026 edition. The Corps text doesn't say which one it means.

To see what's at stake, look at NFPA's summary of the 2026 Article 555 updates, written by Dean Austin in June 2026. It lists ground-fault protection settings no higher than 100 milliamperes on feeders and branch circuits, and 30 milliamperes for receptacles providing shore power. Under Section 555.35(D), boat hoist outlets of 240 volts or less need GFCI protection for personnel, and that includes docks at one- and two-family homes. Section 555.10 requires a permanent sign reading "WARNING - POTENTIAL SHOCK HAZARD - ELECTRICAL CURRENTS MAY BE PRESENT IN THE WATER." And Section 555.15 requires modified, repaired or replaced components to meet current code provisions.

Those rules address electric shock drowning. NFPA describes it as low-level alternating current in the water paralyzing a swimmer's muscles, and it's a bigger concern in fresh water like Lanier than in salt water. NFPA's article points to private docks on residential lakes as places where the hazard is easy to overlook.

Whether a given dock already meets Article 555 is a question for a licensed Georgia electrician, not a real estate agent. The point for a seller is simpler. A dock that has passed recertification under the 1985 standard may be looked at against a different list after January 1, and the amendment doesn't carry over the old grandfather wording.

FAQ

Does the dock permit transfer with the house? No. The Corps' 2026 form says the permit expires when the property changes ownership and the new owner applies in their own name.

Can a buyer ask the Corps whether a dock is in "good standing"? A buyer can ask about a dock's status. The Corps' posted FAQ says it doesn't use the term "good standing," and it may limit what it shares for privacy reasons.

Where do applications go? The Lake Lanier Project Management Office at 1050 Buford Dam Road, Buford, GA 30518, open Monday through Friday from 8 a.m. to 3:30 p.m. You can also email PDFs to [email protected]. The Shoreline Help Desk number on the form is 770-904-3262. The Permit Program page also lists 770-945-9531 for ranger appointments.

Can the dock's authorized spot differ from where it floats today? Yes. The site drawing has to show the authorized location, and the form notes that it may be different from where the dock currently sits.

This post is general information, not legal, electrical or financial advice. Please confirm your dock's situation with the Corps' shoreline office, a licensed Georgia electrical contractor and your closing attorney.

If you're listing a dock home this winter or you're under contract on one, we're glad to walk through your closing date with you before the holidays. Dock permits and grandfathered rights are a big part of what we do at Mickey Hyams. We'll help you line up the electrician's letter, the survey and the Corps paperwork so your sale and your dock permit stay on the same schedule. Reach out to us whenever you're ready.